Manual effort before and after
Before: N × m / 60 hours. After: N × ((1 − a) × m + a × r) / 60, where N is monthly requests, m is manual minutes per request, a is the share assigned to automation and r is average human review and rework per automated request. If r exceeds m, automation increases workload.
Translate hours into cash
Fully loaded monthly employee cost / productive hours = hourly cost. Multiply by freed hours and the share actually converted into savings. If headcount and costs stay unchanged, that share may be zero: capacity increased without cash savings. Count additional workload as a full cost.
Payback and ROI
Net monthly benefit B = cash savings − recurring costs. When B > 0, simple payback = setup cost / B. ROI over H months = (savings over H months − all costs over H months) / all costs × 100%. ROI is undefined when costs are zero. These formulas omit discounting and ramp-up.
Worked hypothetical example
Assume 3,000 requests, 8 manual minutes, 40% automation, 2 review minutes, KZT 400,000 employee cost for 160 productive hours, 50% realization, KZT 90,000 monthly operations and KZT 600,000 setup. This frees 120 hours, yields KZT 150,000 cash savings and KZT 60,000 net monthly benefit, with a 10-month simple payback. This is hypothetical, not TalkIT pricing or performance.